PAL Group has launched its district cooling business, expanding its services to offer efficient cooling solutions for clients.
First chilled water supply agreement was signed with Tamouh for Reem Island, marking a significant milestone in our collaboration.
PAL has commissioned its first and largest district cooling plant in the region, boasting an impressive design capacity of 90,000 RT.
Executed a concession agreement with Sorouh/Aldar for the Shams development project, marking a key milestone in our collaboration.
Successfully executed a concession agreement for Capital Centre Phase 4, setting the stage for a major development milestone.
Executed a concession agreement with Sorouh/Aldar for the Saraya Development, marking a significant collaboration milestone.
PAL has been restructured under PAL Cooling Holding LLC, enhancing its organizational efficiency and strategic focus.
PAL commissioned its second plant for Shams Development, advancing our capabilities and expanding our cooling infrastructure.
Executed a concession agreement with Al Qudra Real Estate LLC for the Danat development, marking a strategic partnership.
PAL commissioned its third plant for Danet development
PAL commissioned its fourth plant for Capital Centre, expanding our district cooling capacity.
PAL commissioned its fifth plant for Saraya development, expanding our district cooling capability and supporting regional development.
Executed concession agreements for Najmat Development, strengthening our strategic growth and partnerships.
Expanded Shams plant capacity by 7,500 RT, bringing the total plant capacity to an impressive 12,500 RT.
Converted a supply agreement to a concession agreement with Tamouh, including Tamouh Sector 4, solidifying a long-term strategic partnership.
Expanded Saraya plant capacity by 5,000 RT, achieving a total plant capacity of 10,000 RT, enhancing cooling efficiency.
PAL began the construction of its sixth plant, second for plant for Shams development with a design capacity of 57,000 RT, advancing our cooling infrastructure.
Executed a concession agreement for the Makers District Project, marking a significant step in our strategic development plans.
Initiated construction of Danet Phase 2 plant, featuring a design capacity of 37,500 RT, advancing our cooling infrastructure.
Successfully commissioned the Shams development second plant, featuring a Phase 1 capacity of 33,000 RT, enhancing our cooling capabilities.
Successfully commissioned the ADNEC plant expansion, increasing capacity by 5,000 RT to a total of 20,000 RT.
Successfully completed the Tamouh plant expansion, increasing its capacity by 25,000 RT to a total of 70,000 RT, enhancing our overall cooling capabilities.
Successfully obtained licenses from the Department of Energy Abu Dhabi (DOE) for Shams, Saraya, and Danat district cooling schemes.
Successfully acquired licenses from the Department of Energy Abu Dhabi (DOE) for Adnec, Tamouh, and Najmat district cooling schemes.
Initiated construction of the Najmat plant, featuring a substantial design capacity of 103,000 RT, enhancing our cooling infrastructure.
The Tamouh plant expansion, adding 5,000 RT, boosting the plant capacity to 75,000 RT.
Successfully commissioned the new Danat DC plant, featuring a Phase 1 capacity of 22,500 RT, significantly enhancing our cooling capacity.